Research Report
On-site generation assets — reciprocating engines, turbines, fuel cells and solar equipment that convert fuel or sunlight into power at the point of use — are being pulled into the same demand supercycle, but OEM factory capacity, not grid access, is now the binding constraint, with production slots reportedly booked out to 2028.
Diesel remains the default format, holding 68.72% of 2025 unit share, but lead times have moved from a supply-chain inconvenience to a capital-allocation decision: small standby diesel units still ship in 12.00-26.00 weeks, large standby diesel gensets now run 52.00-plus weeks, and medium-voltage switchgear — the equipment that connects a genset fleet to a facility's electrical system — runs up to 72.00 weeks, often the longer pole in the tent than the generator itself. The scarcity has repriced the secondary market: low-hour, tested used and surplus units that historically traded at 40.00%-50.00% of new-unit price now command 60.00%-75.00%. Caterpillar's total company order backlog reached a record $63.00bn in the first quarter of 2026, with its large reciprocating-engine backlog having grown more than 3.50x since January 2024, meaning a generation order placed today competes for the same finite factory capacity as every other buyer's.
OEMs are diversifying the fuel-and-technology mix and bundling adjacent hardware to route around the bottleneck: Wärtsilä has booked more than 2.00 GW of US data-center engine orders since the fourth quarter of 2025, including a roughly $333.50mn order for up to 1.00 GW of phased capacity from Liberty Energy, while INNIO booked a 1.10 GW order for containerized Jenbacher gas engines. Generac acquired Enercon Engineering in February 2026 to add switchgear and power-distribution manufacturing to its platform, following its 2024 acquisition of PowerPlay's commercial battery storage business, while Kohler Co. closed a transaction establishing Kohler Energy as an independent business majority-owned by Platinum Equity. On the solar side, two years of tightening tax-equity conditions forced consolidation: Pine Gate Renewables filed for Chapter 11 bankruptcy and was resolved through a roughly $1.40bn-$1.50bn credit-bid sale to Brookfield, Carlyle and Fundamental/FP Solar, while PosiGen was acquired by Renewbrook Energy and SunStrong Management after its own bankruptcy filing, and FuelCell Energy raised $225mn alongside a new data-center pipeline deal.
Free access is capped at two reports per business domain. Personal email IDs are not accepted.